Project
Estimate summary
| Division | Description | % of Total | Scope $/SF | FMI MH | FMI Labour | FMI Material | FMI Total | Trade Total | Total |
|---|
Divisions
Division
Add a trade scope
Self-perform / own-forces breakdown
FMI's own-forces detail for this division — quantities, labour and material, plus any amount carried directly on a line. Trade prices belong in the scopes above; use this breakdown only where FMI self-performs the work or carries a figure itself.
| Group | Description | Qty | UoM | MH | Rate | Labour $ | Mat/Unit | Material $ | Carried Trade $ | Line Total |
|---|
Optional prices
Optional prices are shown to the client separately — they are never included in the bid total.
| Description | Amount | Notes |
|---|
Issue CM Summary to Client
Generates the standard FMI CM recommendation page from the live estimate: every bidder’s final number, the CM Recommended trades highlighted green, and the total of the recommended trades. Built from what is in the estimate right now — check the Summary tab’s warnings first.
Issue Estimate Summary (hard bid)
Internal version with more detail than the CM Summary: under each carried quote it lists the quote's exclusions / scope gaps — pre-filled from the stored quote text and the learned gap library, and editable in each bidder's details. Gap rows with an FMI budget inserted print RED, signalling the summary still needs clarification there. Gap budgets on CM Recommended trades are included in this summary's total. The CM Summary above is unchanged.
Gap pattern library
Gap wording the team has finalized on past estimates, keyed by division and keyword. When a new quote's exclusions mention a pattern's keyword in the same division, that pattern is offered as a pre-filled gap row.
Loading…
Activity on this estimate
Everything that happens on this estimate is noted here automatically — bidders added, quotes received, CM Recommended changes, extra prices, summaries issued.
Private — GE build-up & GE analysis
Only Ryan and Fereshteh can open this tab — the server refuses it for everyone else and the data never appears in anyone else's payload. The build-up below sits behind this job's single Div 01 GE carried line; its total feeds the project total exactly like Div 01.
Loading…
Rate library — $/SF by scope
Two bands: small job (up to SF) and big job. Rates come from actual carried prices on completed estimates (see history below) and are validated by Aritzia. Edit a rate and press Save on its row.
| Scope | Division | Small job $/SF | Big job $/SF | Source / note | Updated |
|---|
Actuals vs library
Every recorded actual: what a scope really carried, against the library rate for its band.
| Project | Scope | Area (SF) | Carried $ | Actual $/SF | Library $/SF | Variance | Band | Source | Date |
|---|